In the oxygen-converter shop of the Dneprovsky metallurgical plant (DMZ, Dnipro), a major overhaul of the converter No. 1 was carried out with the replacement of the neck and the tapered part.
The renovation took place since December 2020. The workers of the metallurgical equipment repair shop dismantled the old converter neck and installed a new one, which was cast in the molding shop.
During the repair, 3.5 rows of metal structures of the tapered part were replaced, which required the completion of about 120 meters of welding seams.
In March, specialists from the metallurgical furnace repair department joined the process. For 10 days they laid a new masonry. This time, Polish-made bricks were used for lining, the guarantee for these refractories is 2100 heats instead of the standard 1900.
As of today, converter # 1 has been put into operation after overhaul, converters # 2 and # 3 are in reserve.
Subscribe to news
Metallurgy news
- 18 November 2024
14:03 Voestalpine does not expect recovery in Germany until spring - 15 November 2024
13:28 Liberty Steel announces plan to restructure Specialty Steel UK - 28 October 2024
20:21 NLMK Verona modernizes sheet metal technology - 20 October 2024
20:38 Ukrainian steel producers will suffer from the Carbon Emissions Management Mechanism - 16 October 2024
17:03 Worldsteel selects a new chairman - 02 October 2024
14:02 SSAB signs agreement with Norwegian company to supply fossil-free steel - 27 September 2024
12:38 Nippon resubmits application for US assessment of USS acquisition - 23 September 2024
23:10 Logistics problems ArcelorMittal Krivoy Rog
Publications
22.11 Creation of unique candles: how to choose the best additives before wax? 21.11 MFO - how to find the ideal place to take out a loan 21.11 Advantages of industrial lamps 18.11 Abrasive materials for cars 17.11 Protection of intellectual property rights