On September 27, the company reported that Brazilian steelmaker Usiminas was forced to shut down blast furnace # 2 at its Ipatinga plant following the September 24 incident.
The shutdown can last from 90 to 150 days, "depending on the repair solution that will be implemented," the company said in a statement.
A blast furnace in the state of Minas Gerais resumed operations in June after an eight-month shutdown that cost Usiminas Real $ 67 million ($ 12.5 million).
According to the company, the equipment is capable of producing 600,000 tons of pig iron per year, which is about 13% of the total capacity of Usiminas.
“The company expects to compensate for the decline in crude steel production by using steel reserves and purchasing slabs from the market, which will minimize the impact on the fulfillment of its obligations to customers,” the steel producer said.
In August, Usiminas resumed operations at its blast furnace # 1 and steel mill # 1 in Ipatinga, as well as at the Cubatao rolling mill in São Paulo state, after operating only blast furnace # 3 in Ipatinga between April and August 2020. ...
Unit 3 has a capacity of 2.9 million tons per year, and unit 1 - 1.4 million tons per year.
Brazilian company Usiminas shutdown blast furnace No. 2 in Ipatinga after the incident
|
Azovpromstal® 28 September 2021 г. 09:12 |